The Mission of the City Streets Department is to provide Street and Bridge Maintenance, Snow/Ice and Emergency Response Control to the citizens and Visitors to Mountain Home so that safety, and the streets infrastructure is maintained in the most effective and efficient manner.

 

 

Mountain Home Street Depart.

2903 Hwy. 201 North

Mountain Home, AR 72653

 

Our Office is open between

7:00 AM and 3:30 PM

 

870-425-4708 (Office)

870-425-9034 (FAX)

street@mtnhome.com

 
Street Committee Meeting November 8, 2011 – 12:30 p.m.

The meeting was called to order at 12:30 p.m.

Present were Amon Tilley, Director of Streets; Darrel Bennett and Rick Pierce, Committee members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for October 2011 was reviewed.

Amon reported another section of the McClure/Glenbriar Rebuild project was paved since the last committee meeting. He said a total to date of $717,159.91 has been spent on this project, and estimated completion in early Fall, 2012.

The South Main Street Rebuild project had another section paved also. Amon estimated completion of this project to be the early Spring of 2012. He said this last paving was approximately $18,000, so the approximate total to date for South Main Street is at $381,493. He added that storm drains, sidewalks, landscaping and paving is left to do.

The Fuel line item is reported in good shape. Rick asked Amon how ready the department was for winter. Amon said the bins were full of sand and calcium and they are ready for winter.

The meeting adjourned at 12:35 p.m.


Street Committee Meeting October 11, 2011 – 12:30 p.m.

The meeting was called to order at 12:32.

Present were Amon Tilley, Director of Streets; Rick Pierce, Dave Almond and Darrel Bennett, Committee members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report from September was reviewed.

Amon reported the McClure/Glenbriar Rebuild project was going well and he'd like to have another section paved. He said the area from the mobile home park to Hallmark will be ready later this week or the beginning of next week. To date, $292,225 has been spent on this project.

The South Main Street Rebuild project is going well. Total to date spent on this project is $292,551.71.

The Microseal project is completed at a cost of $162,938.55. Amon reported he is happy with the way the 19 streets and 1 parking lot turned out. Dave added, he lives on a street that was sealed and said he was also happy with the results.

Amon reported he needed to transfer money from three line items to others to cover expenses. Amon and the committee reviewed the items and after discussion it was agreed the Mayor would draft a resolution for the transfers.

Rick spoke of the shortfall in General Fund and voiced his opinion; the Departments that were not in financial distress should not be penalized for the Departments that are overspending. Also discussed was the possibility of an 18% charge to the Street Department by General Fund for Administrative fees. This amount would come to $64,256 for the year 2012. Water Department would be responsible for 53% or $222,633.63. Rick then reminded the Committee there would be expenses for the Department next year when the 201 South rebuild project begins.

The meeting adjourned at 1:20 p.m.


Street Committee Meeting September 13, 2011 – 12:30 p.m.

The meeting was called to order at 12:30. Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee members. Also present was Janet Nelson from the Baxter Bulletin.

Street Reports were distributed to all in attendance.

Amon reported the McClure/Glenbriar Rebuild project was going well with a cost to date of $237,078.71

South Main Street rebuild is at $252,803.22 to date.

Traffic lights have been upgraded to LED lights by the State Highway Department. Amon reported that he had inquired about upgrading the lights in the past and said it would be costly for the City to upgrade the 22 traffic light locations. He added the lights are controlled by the state and maintained by the City. The upgrade was at no cost to the City.

The Microseal project was started yesterday. Vance Bros. from Little Rock was the low bid for the project. They have started at Chestnut Hills and are sealing various streets throughout the City.

The Committee discussed the site triangle issue. It was agreed a line connecting points 35 feet from the intersection of a collector or arterial street, and 25 feet for the intersection of 2 local streets. The committee agreed to send the ordinance to the Council for approval. Rick announced he would retype the ordinance and give copies to City Attorney Roger Morgan and City Clerk Brian Plumlee.

The meeting was adjourned at 1:27 p.m.


Street Committee Meeting August 16, 2011 – 12:30 p.m.

Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee members.

The Street Report for July 2011 was reviewed.

The McClure/Glenbriar Rebuild project was going good with a cost to date of $142,534.44. Amon was hopeful they would try to pave a portion of the street from the mobile home park to the bypass by weeks end.

The South Main Street Rebuild project is at $148,511.27 to date. 1,200 feet of this road was paved this past Monday from 10th Street to just north of 12th Street by the cemetery.

Crews worked on a City parking lot getting it ready for the new location of the Farmers Market. A total of $6,044.97 was spent on the lot.

Reviewing the Budget summary, Rick asked Amon about the two pickup trucks that came in under budget. Amon reported the pickups that were sold in 2008 and 2009 had a cost of approximately $193.19 per month, based on four trucks. He was asked how long the trucks had been used, and he reported two were at 26 months; the other two were at 27 months. Amon said it's a good deal for the City and has been done for quite a few years, all of the committee agreed.

Bids for slurry seal were opened on August 2nd and they are under advisement with the engineer, Consolidated Land Services. Amon is going to West Plains, Springfield and Joplin, Missouri to look at the their streets that were done so he can compare the work of the contractors along with the sealer that was put down. He said both cities have streets that have been sealed in excess of ten years. They both had two different contractors and two different types of sealer put down. Both contractors placed their bids with the City on the 2nd. Amon added that a decision needs to be made so it can be done during this years' construction season.

Amon asked the committee if he could purchase another plow and spreader to put on one of the 1-ton trucks this year for snow season. He said he'd like to use money that was left over from the line item for the backhoes and purchase a plow and spreader. He told the committee that the spreader and plow that was purchased last year for one of the 1 tons worked out really well for snow removal in the subdivisions. Amon said there is approximately $17,178 left in that line item. He said it will cost approximately $6,097 to put a spreader and plow on the truck. All of the committee agreed, but it needs to go to Council because it's changing a line item.

Residents from the Indian Creek subdivision voiced their concerns regarding a fence that had been put up on the lot at the corner of Oak Ridge Road and Osage Lane. The fence is obstructing site angle view and is also in the right of way. The committee referred it to the Council.

Rick reported maps were distributed to all the schools for traffic relief.

The meeting adjourned at 2:10 p.m.


Special Street Committee Meeting, July 12, 2011 – 12:00 p.m.

The meeting was called to order at 12:05 p.m. Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee Members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for June 2011 was passed out and reviewed.

The McClure/Glenbriar Rebuild project was going good with a total spent of $116,306.57.

Amon reported that he had hoped to have the paving done on South Main Street before school starts, but he said it will not be done to Wade Street. He's hopeful it will be done from 10th Street down to 12th Street by that time. Total to date on the South Main Street Rebuild project is at $104,977.20.

$89,629.91 has been spent to date on Overlays.

The budget looks to be in good shape and Amon reviewed a few line items with the committee.

The Street Department has received the two (2) new ½ ton pickup trucks that had been ordered. There will be 2 trucks put in the City auction next Tuesday, July 19th.

The asphalt recycler bids were opened on July 7th. The bid that was received was too high, so it was rejected. Amon said he wasn't sure if he was going to wait until next year to rebid or try to find different brands of recyclers for review.

Two backhoe bids were accepted and ordered, but have not been delivered yet.

Bids for microsealing various streets were published with the bid opening scheduled for Thursday July 28th.

Rick asked Amon if there was any progress on the retention pond at Cooper Park. Amon reported the design is complete and it's ready to go, he was waiting for the Parks Committee. Rick asked Amon If he had the men and equipment to do this project. Amon said a crew would work as time permitted; he wasn't going to stop a project to work on the pond.

The meeting adjourned at 12:25 p.m.


Special Street Committee Meeting, June 22, 2011 – 9:00 a.m.

The purpose of this meeting is to review a proposal from Arkansas Highway Department for a Highway 201 South widening project.

Present were Amon Tilley, Director of Streets; Rick Pierce and Darrel Bennett, Committee members; and Mayor Osmon. Also present was Richard Hester from KTLO Radio.

A proposal was passed out from AHTD and was reviewed. It included four (4) alternate choices for reconstruction.

The Mayor said he would like to accept the proposal with a portion of Alternate 3 along with a portion of Alternate 4, and request that curb and gutter with sidewalk on the south end be put in from 16th Street to the bypass. The Mayor said that he has received requests from the school to put a sidewalk on the South side from the school to the library.

Rick said he'd like to review all three of their proposals and put a proposal from the City along with it for their approval.

Rick made a motion to present the council with the proposal with the revisions, Darrel seconded.


Street Committee Meeting, June 14, 2011 – 12:30 p.m.

The meeting was called to order at 12:35. Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee members; Richard Hester from KTLO Radio and Janet Nelson from the Baxter Bulletin.

The Street Report for May 2011 was reviewed.

Amon reported the McClure/Glenbriar Rebuild project was going well. The first phase is about 1/3 done. To date $84,116.51 has been spent.

The South Main Street Rebuild project is at $69,377.46. The curbs are in from the cemetery to 10th Street on the East side. The crew has started on the West side.

Overlays are at $86,462.44.

Amon told the committee bids were opened on June 7th for the Asphalt Recycler. The bids were rejected because they came in over what had been budgeted. Amon is not sure if he is going to rebid it later this year or again next year. He said he had budgeted $52,000 and the bids came in at $55,000. Rick asked Amon if he had contacted the company as to why it came in at that price, Amon said he didn't get a satisfactory reply.

The bids specs are almost ready on the slurry seal for various streets. Consolidated is working with Amon on the specifications. Amon handed out a list of streets that will be done in micro seal. The savings will be approximately 40% over hot mix. Part of the savings will be on the driveway aprons. Amon explained that when a street is overlayed, the driveway aprons are included with the asphalt. He added that throughout the neighborhoods, as much money or more is spent on driveway aprons. With micro seal, the aprons will not be done; just the street. Amon hopes to have the bids finalized by next week.

Rick reported that he and Amon met with the Mayor last week to discuss the City accepting Highway 201 South (South College Street) from 9th Street to the Bypass. Also included would be the 201 Spur. He said this has been discussed with the Highway Department and there is a good chance they will do a "cooperative measure" with the City to accept the street and paperwork is getting underway. Rick reported the whole street will be rebuilt from 9th Street to the Bypass. The Highway Department will propose an offer and the City will revise it and then accept it. The State will give both streets to the City after the work has been completed. The Highway Department would do the reconstruction on the street. The savings on the City's part would be approximately 50% or more, by letting the Highway Department do it their way. Rick said he didn't have any numbers yet so he wasn't going to report any. He added we will have to save the funds for the state and then pay the monies out when the bid is let. Though the State would not need any funding until the bid is let, thus giving us a few years to reserve the money from the Street Department budget once the cooperative  agreement is signed and completed. Amon added this is the way it will get the street done quicker. He said this could be completed within the next 3 to 4 years. Previously, when he spoke to the State about rebuilding the street, he was given a 12-15 year completion date on their schedule. Rick added that the Highway Department will give the City the street at any time, but if the City accepts it right away, they will have to do the reconstruction themselves.

Rick announced there will be a meeting between the City and Mountain Home School in reference to the street issues on South College at the Pinkston school access.

Future projects include opening up more roadways with access on the West side of town.

The meeting was adjourned at 1:10 p.m.


Street Committee Meeting, May 10, 2011 – 12:30 pm.

The meeting was called to order at 12:32. Present were Amon Tilley, Director of streets; Rick Pierce, Dave Almond and Darrel Bennett, Committee Members; and, Janet Nelson from the Baxter Bulletin.

The Street Report for April 2011 was reviewed.

Amon reported the McClure/Glenbriar project has started up again after the crew was pulled off and sent to the Police Department to work on their parking lot. Total spent to date at Glenbriar is $63,327.23.

South Main Street Rebuild is coming along good. A total of $37,187.65, to date has been spent on this project.

The project at the Police Department building and sidewalk is at $12,421.07 and this amount will be reimbursed to the Street Department. The parking lot project is at $6,755. Amon reported new asphalt will be put down today.

Overlays have started and as of today, 8th Street and Justis Street have been done.

Sealed bids for new backhoes were opened April 28th. Potter Equipment in Harrison has the low bid with their Case backhoes at a price of $74,116 each. Amon reported the 2 backhoes being traded in are priced at $44,950 and $42,750 for a total trade in of $87,700. This makes the 2 new backhoes a total of $60,532.

A traffic accident at Highway 62 and Cardinal Drive claimed the life of a traffic control box. Amon reported everything is repaired and all information has been submitted to Farm Bureau Insurance for the $15,158,76 claim to be reimbursed to the City.

Rick asked Amon if there was any progress on the information for using the used traffic light poles for the ball field lighting. Amon said Consolidated Land Services is still working on it, waiting to hear from the manufacturer of the poles for the specifications along with the Highway Department.

Rick also asked about the Cooper Park drainage. Amon said all that had been done so far was the survey. Rick would like to have the creek dammed so there could be a retention pond at the back corner of the park.

The meeting adjourned at 12:51 p.m.


Street Committee Meeting, April 12, 2011 – 12:30 p.m.

The meeting was called to order at 12:33 p.m. Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee members; Richard Hester from KTLO Radio and Janet Nelson from the Baxter Bulletin.

The Street Report from March 2011 was reviewed. Amon reported curbs are going in on the McClure/Glenbriar Rebuild. To date, $47,731.54 has been spent on this project.

There is a crew working on South Main Street. It will be completely rebuilt from Dodd Street to Wade Street. They have started at the North end, to get that area done before school starts next year. Amon said the whole project would most likely be completed by then. New culvert, curb and gutter, and sidewalk will be going in.

The Laurel Road Box Culvert project has been completed at a cost of $21,208.63.

The Gregg Road Rebuild is completed with a total cost of $164,241.58.

Amon reported the Budget was still in good shape. Rick asked how the fuel costs were. Amon said they were doing pretty good so far, with a lot depending on what happened this summer.

Rick asked Amon where they were with the Parks Department and their lights. Amon told the Committee that Consolidated Land Services is conducting tests on the poles. They had been out and took measurements they needed to see if the lights the Parks Department has would be supported by the poles. Amon reported to the committee that the Street Department has heavy-duty traffic light poles that had been taken down in the past, and the Parks Department acquired lights from the stadium in Fayetteville. The Engineering firm is running tests to see if the lights can be supported by the poles. They have also been in contact with the light pole manufacturer.

Rick mentioned the Parks Department is going to be putting up new fence at Cooper Park. He asked Amon if the Street Department was going to assist with equipment or how was that done. Amon told him it hadn’t been mentioned, but he would help in any way if they needed it. There was also discussion about the creek at Cooper Park, which Amon said he’d take a look at.

Rick asked Amon if the Street Department was done working at the new Police Department. Amon said there still needs to be a curb put in at the upper parking lot next to the building, and they will get started on it next week.

Rick brought up the Water Department’s request to be able to park their trencher at the Street Department. The reason for this is it is so big and unsightly; they’d like to move it to an area out of the way. The Water Department also has other acreage it could be parked at. Rick said he had met with Amon, and they agreed there was no room for the trencher. Dave suggested they put up a fence to hide it, or since they have other property to keep it on, that’s where they should keep it. Rick also mentioned that the Water Department could move it closer to their building, and it would be away from the road and it would blend in with all of their other equipment. All agreed that the trencher will stay at the Water Department.

Amon presented an ordinance that will go the Administrative Committee. He said since Section 3 had been added it pertains to the Street Department and would like to see it passed as it’s written. Rick added the last one had a $4,000 amount in it for the Council that was sent back to committee. He said there was a discrepancy between the $20,000 and the $4,000. He added this was all directed at used equipment purchases, or any equipment of any kind that is not a line item. This give the department the ability, if it’s $20,000 or less, to make the purchase without going to Committee or Council for approval.

The meeting adjourned at 12:57.


Street Committee Meeting, March 8, 2011 – 12:30 p.m.

The meeting was called to order at 12:30 p.m. Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for February 2011 was reviewed.

The crews are doing a final dig out at Gregg Road in Carlile Highlands. All the concrete work is done, and there is base, paving and landscaping left to do. To date, $110,023.19 has been spent at this job.

The McClure/Glenbriar Rebuild job has the crews working on curbs. Storm drains are in from the church, south to the bypass. $18,697.49 is the total cost to date.

The box culvert at Laurel Road is in at a cost of $6,205.95 to date. Curbs are being put in over the top of it today, and wing walls have yet to be put in. The street should be opened back up by Thursday.

Two Snow Removal reports were included this month. One is a current report, for 11/15/10 through 2/28/11; the second one is for 11/15/09 through 2/28/10. The total cost of Snow Removal for this year was $39,073.47. Last year was $89,272.89. Amon said the breakdown compared the two years.

The Budget is in good shape, Amon reported.

Rick asked Amon questions concerning the McClure/Glenbriar project. Amon said this project would be a two-year project, with a total cost of approximately $1.5 million dollars. The first phase of the project will go from the bypass to the trailer park; the second phase will go from the trailer park to the 4-way stop at McClure. The last phase will go from the 4-way stop to Highway 5 South.

Rick asked Amon if his department was on schedule with this project. Amon said it was, and the weather didn’t hold them up that much.

Rick also asked about the street being opened at the Laurel Avenue box culvert. Amon told him that the concrete had to completely cure before the street was opened, and he felt that Thursday would give it enough time to cure out.

Amon reported he spoke with a company a few days prior regarding slurry sealing various streets. He said he had some streets sealed in the past, and it was a good product, adding, the public needed to be educated what is done. Slurry seal, or micro seal is done on a good street, to keep it good. This would mean a street that is five years old would be sealed. It is very good preventative maintenance. Amon reported, if you have a street that is 5 to 8 years old, slurry seal it, and the street will be good for another 8 to 10 years. After that, put another slurry seal on it and you’ll never have to overlay that street. Rick mentioned that the problem with slurry seal is that it’s not a “politically productive decision” because it seems that the streets are being painted. However, he added that in the long run, the street is being saved. He said it’s a better decision for Mountain Home, because the street can go from being a 10 to 15 year street, to be made to last 25 or 30 years. The short term, residents will think the street is just being painted. Rick gave an example of when he and Amon had a prior discussion about a street that could have been slurry sealed approximately 5 years ago, he said, had the street been slurry sealed, it would not have to be overlaid, and that street in particular is scheduled to be overlaid this year. Rick said this will be so much savings to the City compared to overlaying. He added, to run a grinder on the road and then to overlay it would have so much more cost compared to slurry sealing, and it was a very valuable process. He said he and Amon were both in favor of it. Some of the streets that had been slurry sealed back in the 70’s and 80’s continue to be good streets, however, streets that are next to them have started to fall apart. It’s very difficult when the surface cracks, water gets in, it freezes and starts to tear the pavement up. The slurry seal saves that. Amon said there are a few issues with slurry seal, one is getting a set of specs that you can follow, and make sure the company is following it. The State Highway Dept. has specs, but they are such a wide-range that you get some of them in. There was a company that came in 6 or 7 years ago and did some slurry sealing. It didn’t hold up, there were problems with the company, and Amon said the City had to threaten with lawsuits and even held back money until the issues were resolved. They were within the boundaries of the mix design, but they had changed it one way or another and it wasn’t right. He showed a sample of a product that was put down on streets at West Plains, Missouri last year. MAQS surfacing system is the product, it is similar to a micro seal, but there is no comparison. He said it is a real hard rock, and he doesn’t like the micro seal because if there is a softer rock in there, it won’t work. West Plains is doing some of this he said, and Springfield Missouri is doing a lot of it. This is another option he has. It will do a street that is a little rougher, that the slurry seal won’t work well on. Another issue with slurry seal and others is you need to know what kind of street you are going to put it down on. It cannot be put down on a street that is worn out; money will be wasted on that street. Amon said it would on the street that he and Rick discussed. Amon said the MAQS sealer is about half the cost of asphalt.

The meeting adjourned at 1:00 p.m.


Street Committee Meeting, February 8, 2011 – 12:30 p.m.

The meeting was called to order at 12:31 p.m. Present were Amon Tilley, Director of Streets; Rick Pierce, Darrel Bennett and Dave Almond, Committee members, Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for January 2011 was reviewed.

Amon reported weather permitting, digging out for the Gregg Road project will begin next week and paving would be done in the Spring. Total cost to this project through January 31 is $90,427.57.

The cost of snow removal through February 6, 2011 is $18,032.11.

A crew started yesterday working at Glenbriar for the McClure/Glenbriar street rebuild. This project is going from Highway 5 South to the Bypass.

Amon reported to the committee that a 1-ton truck purchased from Federal Surplus last year was fitted with a V-plow and sand spreader. He said the truck cleans up the snow quicker than the dump trucks, and he’d like to purchase a spreader for another 1 ton that the Street Department has.

A Mountain Home resident from Louann Drive complimented Amon on the job well done removing the snow. He also asked what the Equipment Cost was on the Snow Removal report. Amon told him that each piece of equipment had a cost per hour charge. The resident also asked Amon why the plow trucks would drive down his street when the snow was already plowed. He told the man the trucks do passes and go wider each time around. Amon told him the City is divided up into 10 Zones. He said each Zone has main streets that get plowed first, and then the secondary streets get done. He also added, the plows need to get to the edges of the road to keep the inlet boxes clean so the water has some place to go when the snow melts. This is the reason they keep going down the streets, widening as they go around. The resident also asked what the guys in the pickup trucks are doing “riding around”. Amon told him they are supervisors that are checking the streets as they are being cleaned. There are also crews in pickup trucks cleaning the culverts out so the water will drain. Rick asked the man if he had noticed the trucks going around Monday and Tuesday of this week. He said there were crews going around cleaning up the broken asphalt throughout the Zones. Amon said there is a lot more than getting into a plow truck and going down the road and cleaning it off once. It just doesn’t work that way. He commended his crew for doing a fine job getting the streets cleaned in a timely manner.

The meeting was adjourned at 12:42 p.m.


Street Committee Meeting, January 11, 2011 – 12:30 p.m.

The meeting was called to order at 12:30 p.m.

Present were Amon Tilley, Director of Streets; Darrel Bennett, Dave Almond and Rick Pierce, Committee members.

The Street Report for December 2010 was reviewed.

Dave nominated Rick for Committee Chairman, Darrel seconded.

Amon reported the crew working on the Gregg Road project has the curbs done and have been putting in sidewalks. The street will be ready for paving in early Spring. The cost to date for Gregg Road is $74,305.19.

A crew has built a retaining wall at the new Police Department on W. 7th St., to dump fill between the empty lot and the creek. Amon said it’s a good place to put road fill. The cost of this project to date is $30,554.05.

Amon reported he had a crew come in about 4:30 a.m. on Monday, and another crew came in around 5:00 this morning to put sand/calcium down at the main intersections and slick spots throughout the city. He said the problem with this amount of snow is it cannot be plowed, they have to rely on the sun to melt it, and sand will be spread.

Rick asked Amon what street projects he had planned for this year. Amon said the Gregg Road project at Carlile Highlands would be finished this year. He said McClure from Highway 5 South and Glenbriar to the Bypass would be completely rebuilt this year with curb and gutter, sidewalk on one side. Amon added he is in the preliminary stages of looking at South Main Street from 10th Street to Wade Street. One of the problems is the right-of-way by the little houses. It’s in the planning stage right now and if there is room to fit it in, they’ll try to do it. He also said the school at 10th and Main is closed right now but it will be open next year. It would be to the city’s advantage to get the road rebuilt before the school is opened back up.

It was agreed to keep the Street Committee meeting on the 2nd Tuesday of the month at 12:30 p.m.

The meeting was adjourned at 12:37 p.m.


Street Committee Meeting, December 14, 2010 – 12:30 p.m.

The meeting was called to order at 12:30 p.m. Present were Amon Tilley, Director of Streets; Mary James, Darrel Bennett and Dave Almond, Committee members.

The Street Report for November/December along with the year-end report was reviewed.

Amon reported the Gregg Road project is going well with curbs just about finished to Highway 5 South. The crew is working on the sidewalk now. This project will be ready for paving Spring 2011. This project is at $52,136.53.

The retaining wall being built at the new Police Department for the fill being brought in by the Street Department is at $13,418.20.

The Rodeo Drive North Extension project has been completed for a total cost of $671,836.54

Budget is in good shape for the end of the year. The annual report was reviewed. The meeting was adjourned at 12:35 p.m.


Street Committee Meeting October 12, 2010 – 12:30 p.m.

The meeting was called to order at 12:30. Present were Amon Tilley, Director of Streets; Mary James, Darrel Bennett and Dave Almond, committee members; Richard Hester from KTLO Radio and Janet Nelson from the Baxter Bulletin.

The Rodeo Drive North Extension project total is $573,493.13. Amon reported the street would be paved later this week. He added there might be a ribbon cutting ceremony sometime next week. Mary said it is commendable that this project has been finished ahead of schedule.

Amon told the committee the Budget is in good shape. He noted that there would be more money carried over to the 2011 Budget. It will look like there is so much more carried over because there was equipment that was budgeted this year that wasn’t purchased. He said part of the reason the equipment wasn’t purchased was at the beginning of the year the sales tax was down and he wasn’t comfortable buying anything at that time. Amon said those amounts are for two backhoes, a hot mix recycling machine and a dump truck. He said those have added to the 2011 Budget.

The meeting was adjourned at 12:40 p.m.

Street Committee Meeting September 14, 2010 – 12:30 p.m.

Meeting was called to order at 12:30. Present were Amon Tilley, Director of Streets; Mary James, Darrel Bennett and Dave Almond, Committee members.

The Street Report for August was reviewed. Amon reported the 6th Street ditch was completed at a cost of $22,331.90. Rodeo Drive North Extension is going good and will be ready for paving within the next month, weather permitting. Total spent on this project to date is $478,627.29. Overlays total $362,753.21, and Amon reported that this would be it for the overlays this year, other than Rodeo Drive North Extension. The Budget is still in good shape.

Amon and the Committee discussed the combined purchased with the Water Department, an aerial photo program called Pictometry. He and City Engineer Angela Curtis explained that it would work well with both the Street Department and Water and Sewer Department design work. Angela explained the program was similar to Google Earth, but more detailed. Instead of a direct look from above, it would show oblique photos, on an angle. She asked the committees to take a look at it after the meeting was over, as it was on her computer and she could show how it worked. The flyover would take place sometime between January 15 and March 15, 2011, over the city and one mile surrounding the city limits. Amon asked the committee if they would approve the purchase, and if they did, an ordinance would need to be written for a bid waiver. Since the company that does the flyover has a patent on the program, there would not be a competitor for this program. The Street Committee along with the Water and Sewer Committee both agreed to send it to the City Council for a bid waiver. The cost of the flyover and program would be approximately $85,000. Both the Street Department and Water Department would benefit from this program. Amon spoke with Carry at the PD and he said they would be able to use the program on some things.

The meeting was adjourned at 12:47 p.m.

Street Committee Meeting August 10, 2010 – 12:30 p.m.

Meeting called to order. Present were Amon Tilley, Director of Streets; Mary James, Dave Almond and Darrel Bennet, Committee members; Janet Nelson from the Baxter Bulletin, and Ray Dean Davis from KTLO Radio.

Amon introduced Angela Curtis, the City Engineer to the Committee.

The Street Report for July was reviewed. Amon reported the ditch at 6th Street was almost complete. The cost to date is $15,988.87. The Rodeo Drive North Extension is going good. $406,041.77 has been spent on this project. Overlays from 4/13 to 7/31 are at $234,190.68. Amon told the committee they are now doing streets in Indian Creek.

There will be two FEMA Flood Study meetings today at 2:00 p.m. at City Hall and at 6:00 p.m. at the Courthouse. This meeting is regarding any flood map changes.

There will also be a meeting on Thursday, August 12th at 10:30 a.m. on Pictometry. This is a flyover that will photograph the city to show topo’s and showing structures, etc. Amon said this will help with drainage structures, developments, etc.

The Street Department purchased a 2002 Freightliner semi with 20,000 miles from Federal Surplus last week. Amon reported he had budgeted $25,000 for a semi, but found this one at surplus last week for $5,000. He said it was in the Shop now being painted.

Amon told the committee that he had purchased a loader at Federal Surplus and would like to equip it with a snowplow attachment. The cost of the plow is $16,790 and the couplers for it are $6,780. He said he was going to meet with Roger to see if he needed to do a bid waiver on it since it was two items. Also, there is money left over from the purchase of the semi and the trucks that were purchased to cover these costs.

The meeting was adjourned at 12:38 p.m.

*Roger said we did not need a bid waiver

Street Committee Meeting July 13, 2010 – 12:30 p.m.

The meeting was called to order at 12:30. Present were Amon Tilley, Director of Streets; Mary James, Darrell Bennett and Dave Almond, Committee members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for May and June was reviewed.

Rodeo Drive North Extension, Highway 5 North to Walker Road is at $371,262.60.

Nelson Street curbs is complete except for the overlay, which is waiting because of the rain we’ve been getting. Cost of this project is $32,961.15.

Overlays are at $25,458.82

Pine Tree Lane sidewalk is complete except for some touch up landscaping. Final cost of this project is $37,905.65.

Amon read a letter from Arkansas Highway and Transportation Department; they have denied the City’s request for traffic lights at the three locations that were requested for traffic studies, (West Road and Rodeo Drive, Highway 5 North and Rodeo Drive, and, Arkansas Avenue and Highway 201 North). Mary said it was going to be a mess, Amon agreed. He said after the new school buildings are built and the traffic is there, the City will again request another traffic study.

The meeting was adjourned at 12:40 p.m.


Street Committee Meeting May 11, 2010 – 12:30 p.m.

The meeting was called to order at 12:30. Present were Amon Tilley, Director of Streets; Dave Almond, Mary James and Darrel Bennett, committee members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for April 2010 was reviewed. The Arkansas Avenue Phase 3 project has some landscaping left to do and it has been paved. Striping will be done when all the overlays are complete. The cost to date is $274,039.38.

The North Extension of Rodeo Drive is at $317,829.70 to date. It has been paved to just past the storage buildings.

The total to date for Overlays is $12,065.38.

$17,697.57 has been spent on installing French drains, and ditch work was done at the Soccer Field.

A pad for the Soccer Field water tank building was poured for a cost of $1,647.37. This amount will be reimbursed by the Water Department.

The Soccer concession stand has been completed for the cost to be reimbursed to the Street Department of $12,018.75. This is a total of materials and labor for the project and will be reimbursed from the $28,000.

May 3, 2010 a letter was written to the Arkansas Highway Department requesting a traffic study for lights at three intersections in town. They are Highway 5 North and Rodeo Drive, Highway 178 (West Road) and Rodeo Drive, and Arkansas Avenue and Highway 201 North. Amon reported it is hard to get the highway department to project any kind of traffic numbers, but said he pointed out to them that the school is being built at Highway178, and the traffic flow will be increased. He added, whether they take that into consideration or not, he didn’t know. He also said, once the school opens, he’s sure the light will be needed there. Amon said the City could put one in, but the cost is so much. When the light is installed, there is a cost share of 80% coming from Federal, 10% from the State and 10% City. It is a good deal if it would be a cost share, otherwise if the City were to put a light in, it would probably be in excess of $300,000.

The meeting was adjourned at 12:42

Street Committee Meeting April 10, 2010 – 12:30 p.m.

Meeting called to order at 12:30. The Street Report for March 2010 was reviewed.

Amon reported Arkansas Avenue Extension Phase 3 is being paved today. It will finish up today or tomorrow. Mary said this was great and it is very exciting.

A sidewalk is being put in at Pine Tree Lane between the junior high school and high school. The crew is as far as the corner by Rodeo/Pine/Rodeo, about ½ way.

The first section of the Rodeo Drive North Extension will be paved either tomorrow or Thursday, when Arkansas 3 is done. Amon said the crew was not ½ way through yet to Walker Rd.

There are two reports for the soccer field; one is for the building, with bathrooms, and the other report is the maintenance being done. The material that is being used for the building will be reimbursed to the Street Department. The maintenance that is being done at the soccer field is drainage work, trying to get the water out of there. The meeting adjourned at 12:37 p.m.
 

Street Committee Meeting March 9, 2010 – 12:30 p.m.

Called to order 12:30 Present were Amon Tilley, Director of Streets; Mary James, Dave Almond and Darrel Bennett, committee members. Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for February 2010 was reviewed. Amon reported that Arkansas Avenue Phase 3 was done except for the landscaping. It won’t be too long before paving begins for this. To date, $195,310.94 has been spent at this phase of the project.

A total of $89,115.94 has been spent from January 1 through February 28 for Snow Removal.

Rodeo Drive North is going good, the first section will be paved when Arkansas Phase 3 is done, weather permitting.

The meeting adjourned at 12:42  

Street Committee Meeting February 9, 2010 – 12:30 p.m.

The meeting was called to order at 12:30 p.m. Present were Amon Tilley, Director of Streets; Mary James Darrel Bennett and Dave Almond, Committee Members.

The Street Report for January 2010 was reviewed. Arkansas Avenue Extension Phase 3 has the curbs completed and there is a little bit of sidewalk to be finished. This will be ready to pave in the Spring.

The North Extension of Rodeo Drive, from 5 North to Walker Road will be paved to just past the storage buildings in the Spring. This will make it easier for the businesses there, so they won’t have to deal with the dust while the crew is working on the new road.

A total of $58,238.69 was spent on Snow Removal through January 31.

Amon reported the Budget was in good shape, and also the State’s share of the FEMA money, which is 12 ½%, had been received. A total of $151,511.29 was received on January 26, 2010. All of the reimbursement money for the 2009 ice storm has been received. The meeting adjourned at 12:40 p.m.

Street Committee Meeting January 20, 2010 – 12:30 p.m.

The meeting was called to order. Present were Amon Tilley, Director of Streets; Dave Almond, Darrel Bennett and Mary James, committee members; Janet Nelson from the Baxter Bulletin and Richard Hester from KTLO Radio.

The Street Report for December 2009 was reviewed. Amon reported the curbs are done and the crew is finishing up the sidewalk at the Arkansas Avenue Extension Phase 3 project. There is approximately 2 to 3 weeks left to finish up sidewalks and landscaping. The next to the last lift of base is being put down now. The project will sit like this until spring, when the last lift of base will be put down right before paving.

The Rodeo Drive North Extension has curbs done just past the storage buildings. Amon told the committee he plans on spending the winter going across the field. When Phase 3 of Arkansas Avenue is paved, he would like to have the first 400 or 500 feet of the Rodeo Drive Extension paved in front of the businesses out there. This way they won’t have to deal with all of the dirt and dust going on at the project. Mary asked if this would be ready to pave all the way to Cannie Baker in the fall. Amon said probably the spring of 2011. Mary added this will be such a help to so many people.

Amon reported the 2009 Budget finished out in good shape. All reimbursements have been received from FEMA except for the State’s reimbursement. The meeting adjourned at 12:40 p.m.

Street Committee Meeting December 9, 2009 – 12:30 p.m.

The meeting was called to order at 12:35 p.m. Present were Amon Tilley, Director of Streets; Mary James and Dave Almond, Committee Members; and Janet Nelson from The Baxter Bulletin.

Amon passed out the Street Report for November, 2009.

Arkansas Avenue East Extension, Phase 3 is coming along good with curbs. Total spentat this project to date is $134,774.07. Mary said it’s looking good with the curbs.

A crew is digging out for the extension of Rodeo Drive, North, from Highway 5 North to Walker Road. This project cost is at $81,172.20 to date.

The Overlays are finished for the year, Amon reported. Thirteen streets were overlaid for a total cost of $180,217.02.

The 12 ½% of the FEMA reimbursement by the state has not yet been received. Amon called today and said they are checking on it. They will get back to him. This amount is approximately $140,000. While reading the November Street Report, Amon mentioned that $851 was spent on putting up Christmas Lights. A member of the audience, Carl Graves, asked if this was an hourly rate. Amon told him this amount is the cost for the labor and equipment used for putting up the lights. Mr. Graves then asked why it is shown like this, because they are City employees anyhow, and they are just sitting around. Amon told him his employees don’t sit around. This report and all reports show thetime spent for labor and equipment for each job that is done for his department. Amon then added, he shows every minute for his employees time, every day, in whatever they do, whether it’s fixing a pothole, or putting up a street sign or putting up Christmas lights, it’s all part of the scope of their job. But, it’s all itemized out. Mary added, in this department, you will know where it’s going. All of it. Mr. Graves then asked where this money comes from. Amon told him it comes out of the salary line item. He said all the vehicles are prorated on what was paid for that vehicle or equipment, what is costs to operate, and that breaks down to an hourly rate on each vehicle and piece of equipment the department has. If they had one vehicle or two vehicles out there, that is in that figure as to what it costs to operate that vehicle or equipment. All of the daily jobs are kept this way, so they can refer back to other dates, who did what and where they were at. Mary again said in this department, you can see where it’s going, all of the time.

Amon said he has a crew that will be ready to start building a sidewalk from Bomber Boulevard to Pine Tree Lane (from the Junior High School to the High School). The crew will be starting this project when they are finished with the curb and sidewalk at the Arkansas Avenue Extension, which will be in approximately 45 to 60 days, depending on the weather. Mary said a lot of kids are walking back and forth and this needs to be done for safety reasons. Amon agreed, there are a lot of kids over there that walk on the edge of the street.

One more thing Amon wanted to talk to the Committee about was the old culvert pipe. He said he talked to the City Attorney about scrapping it out. Amon wanted to clear it through him first, he said they would take the old culvert to the scrap yard next to the Street Department Shop and turn it in to recycle. He said the money received from this would then be sent to City Hall. The meeting was adjourned at 12:45 p.m.

Street Committee Meeting November 10, 2009 – 12:30 p.m.

The meeting was called to order at 12:30. Present were Amon Tilley, Director of Streets; Mary James Darrel Bennett and Dave Almond Committee Members; Julie Stewart from KTLO Radio and Janet Nelson from the Baxter Bulletin.

The Street Report for October 2009 was reviewed.

Amon reported the crew working on Arkansas Avenue Extension Phase 3 is almost to Commerce Drive. They will be putting base down and then working on the curbs. Total to date on this project is $100,907.13. Amon said he still does not expect to pave this portion until Spring.

The Rodeo Drive North Extension project has a cost to date of $36,701.10. The crew is working on digging out the road right now, and they did put in a little curbing. This project Is going from Highway 5 North to Walker Road.

Maintenance, Sign Maintenance and Traffic Light Bulb Replacement reports were reviewed.

The Budget is still in good shape, and, Amon said Overlays had been started last week. Streets will be overlayed, weather permitting. He said any streets that are on the list and not done this year will be picked up in the Spring. The meeting was adjourned at 12:35 p.m.

Street Committee Meeting October 14, 2009 – 12:30 p.m.

The meeting was called to order at 12:35. Present were Amon Tilley, Director of Streets; Mary James, Darrel Bennett and Dave Almond, committee members, and Richard Hester from KTLO Radio.

The Street Report for September 2009 was reviewed.

Amon reported Arkansas Avenue Phases 1 and 2 are completed, along with Wallace Knob Road and North Cardinal Drive.

Arkansas Avenue Phase 3 has been started and is cut through. The base is down and the crew has started pouring curbs.

The Street Department has received all but approximately $1,100 from FEMA for reimbursement for the ice storm. Amon said he has applied for the state’s portion of reimbursement, which is 12 ½%. It should take a few months to receive.

The Budget is in good shape, and Amon reported there is a good list for overlays to be done this fall, weather permitting. He said if the weather doesn’t cooperate, the money that will be used for overlays will be carried over to the 2010 Budget and they will be done in the Spring.

A resident from Willow near Bluebird had some drainage concerns with the ditch in front of his house. He said water stands and smells bad. After some discussion, Amon said he would take a look at the ditch to see if anything could be done. The meeting was adjourned at 12:55 p.m.

Street Committee Meeting, September 9, 2009 – 12:30 p.m.

The meeting was called to order at 12:30.

Present were Amon Tilley, Director of Streets; Mary James and Dave Almond, Committee members; Richard Hester from KTLO Radio; and Janet Nelson from the Baxter Bulletin.

The Street Report for August 2009 was reviewed.

Amon reported Phase 3 of the Arkansas Avenue East Extension has been started. The crew is ready to start putting base on it.

The cost of the North Cardinal Drive project is at $126,352.39 to date.

Weather permitting, Twin Lakes Quarry’s will be paving Phase 1 and 2 of the Arkansas Avenue Extension tomorrow or Friday. The equipment is there and it is ready to start.

Amon told the committee the Street Department’s part of the Keller Park Walking Path is completed. He said the Parks Department had some things to do on it.

The project at Wallace Knob Road is at $91,295.70 to date.

Mary announced that the both Wallace Knob Road and North Cardinal Drive projects were two streets being improved with new drainage, sidewalks and curbs as part of the Arkansas Avenue East Extension project.

A crew will be starting tomorrow on the Rodeo Drive North Extension. This project will go from Highway 5 North to Walker Road. Mary added this is very exciting because it will open up the Walker/Cannie Baker area and those residents will be able to use this to get to the Hospital and the school. A question was asked if traffic counts will be conducted soon so a traffic light could be put up at the time the street is completed. Amon said traffic counts will be done by the state and will not be done until the road is completed.

Residents from the Langston Subdivision brought to the committee meeting concerns about flooding. The meeting adjourned at 1:20 p.m.

Street Committee Meeting, August 11, 2009 – 12:30 p.m.

The meeting was called to order at 12:30 p.m.
  Present were Amon Tilley, Director of Streets; Mary James and Dave Almond, Committee members.  

The Street Report July 2009 was passed out for review.   Amon reported the first lift of asphalt was put down on E. Arkansas Avenue and in two weeks Kings will be back to put the final lift on it and that will put Arkansas paved from North College Street to Cardinal Drive, along with Wallace Knob Road and Cardinal Drive being paved also.  

The ditch at North College Street and Coley Drive has been completed.

Easements have all been signed for the North extension of Rodeo Drive. The engineering is being done on it now. This will come out right across Highway 5 North at Rodeo Drive and continue through the storage buildings and come out at the intersection of Walker Road and Cannie Baker Road, right by the J & L Service Station. Mary mentioned in addition to the street easements being signed, also signed were the easements for water lines. Amon reported the crews will start in approximately 45 days, it will be approximately a $475,000 project and the work will be completed late 2010 or early 2011, depending on cash flow.  

Dave asked Kent Smith from Century 21 address the committee. Mr. Smith passed out copies of a color-coded plat to the committee in reference to a lot on Parkview in Indian Creek. He said this plat was zoned in 1972, Cardinal Drive did not go through yet, it stopped at the subdivision. He added with the area just beginning, a lot of the regulations were not in force at the time, as they are now. He said to the left of the plat was Cardinal, and then there was a section next to Cardinal that is a main creek that comes from the park. There is another section that varies in width that was zoned by Indian Creek Inc. He said it went back because Indian Creek Inc. does not exist anymore. The yellow line between lot 4 & 5 is a drainage ditch that was just a shallow “V” that they had cut in with the natural flow of the drainage back way when he began in real estate school. He added they had to have a drainage system in there to keep the water out of the street area while they were developing it. The red part is just blacktop that drains down to a cut in the curb between lot 4 & 5. The yellow is two manholes that pick up the water and there is a tube that goes under the street connecting to a tube that goes and empties underneath the cut in the asphalt. There is approximately 5 acres in the orange section the blacktop doesn’t include the roofs that are piped out into the street from the driveway.
  If you just take the blacktop that’s about a 100 x 200 foot rectangle of blacktop parking area plus the roofs and the driveways. The ground area in between the streets is about 5 acres, so you’ve got that much area draining through a little drainage ditch between these two lots. What it does is when you get water then it runs across lot 4, putting in debris and flooding their yard. Lot 5 on the North side of lot 5 there is a major wet weather spring. And, if you look, there is a cut, at least probably a foot wide and 8 to 10 inches deep that the water flows from this spring trying to go into this drainage ditch. This lot 5 is owned by Willett. When water runs, and the spring slows down, they have a hard time trying to mow their lawn. It’s so hard to mow you can see tractor tracks. Mary said, if it’s his (Willett’s lot), it’s his responsibility to take care of that.  

Mr. Smith said he had no idea whose responsibility it was, but he said he knew that there is water dumping on the lot of these people’s house he sold to. Mary asked if this was part of the floodplain, Amon told her yes. Amon said he’d like to clarify a couple things. He said the regulations we have today still allows this. This is not unique to this area by no means, he added. Every subdivision in down, water is running down lot lines, from the newest ones, to the oldest ones. Water will end up going in the low point and that’s exactly what it’s doing there. The City does not maintain any of them, outside of the city right of ways, we do maintain the main creek channels that we have easement on. That creek channel that you have in blue there, we do have an easement on and we do maintain that main channel. But, your little side ditches that come into it, that come across private property, are strictly that, they are on private property.
  Unfortunately, when a subdivision is designed like this, if this subdivision was designed today, it would probably be designed the same way because the water has to go to the low point and that is the low point in the subdivision. The owner of the property in question, Joan Cedron, asked Amon if anybody has approached Mr. Willett concerning this situation. Amon told her if he were a neighbor, he would have approached Mr. Willett. He also said the City doesn’t really have a say so in this matter. It isn’t up to the City to go to Mr. Willett and tell him to change his property. She said she understood, and she only found out the other day that he was the owner of the lot. She said she would be more than happy to talk to Mr. Willett about working something out to fix the ditch. Amon said that would be how he would approach it if he lived there. The normal design for it was that water should be going down the property line, and at one point it did. He said the yard and the house she lives in had been filled in from the first time. He also said he looked at this problem 20 years ago and different people have come in put dirt in the yard to move the creek channel a little further away from the house, more towards that vacant lot. Amon said his recommendation would be for the neighbor’s to try to get together on this. She said she was going to try. Mary said for her to drive around town and she’ll see everywhere in town people have concreted some kind of swale or bricked it or even sloped it. Ms. Cedron said her husband would be more than glad to maintain their side of the ditch if it was cleaned up. Amon said so many of the places get them dug out, it would be wet all the time, but it would be better than what it is. Mr. Smith added there would be a collection of dirt. Amon told him you get that everywhere. Mr. Smith also asked if if was the property owners responsibility to solve the mosquito problem. Amon told him the mosquito problem wouldn’t be there if the ditch drained, and it’s the property owners’ responsibility to keep the ditch drained. Amon asked Mr. Smith if he was aware of this when he sold the property. Ms. Cedron asked Amon, what if Mr. Willett refused to take care of this problem. Amon told her in his opinion it would be a civil matter. Dave added you are liable if you are dumping water on your neighbor. Anytime a neighbor changes something, they are responsible. Amon told everyone that watershed dumped there before the subdivision was built. He asked Mr. Smith if he was aware of all of this before he sold the property. Mr. Smith said he knew there was a drainage ditch, but he didn’t realize it shed that much water. He said he thought the manholes would pipe somewhere, he added he didn’t walk over there to see. Amon said they have to pipe into the ditch, that’s the low point, that’s the only place it’s going to go. He said you couldn’t take this water and take it a different direction, because it’s uphill. Mr. Smith said he thought the pipe went to the creek. Amon said there are only two subdivisions in town that he knows of that have piped the water to the back of the lots, and then when they get to the back of the lot lines, they are turned loose on somebody else’s property. The only two subdivisions that are done that way are Big Creek and Savannah. The City regulations do not require them to do that, they can bring it out to the back of the curb and dump it and let it run down the lot lines. Mr. Smith asked about the ditches at Southern Meadows, he asked Amon who put those in. Amon told him the main creek channels were done by the City, but the shoots in between them were done by the developers or property owners. He added he took Dave and Mary both around and showed them some of the work done by different property owners that he had talked to before. He said some put low concrete shoots in, a lot of them had put in brick and blocks along the side of it. Dave said his neighborhood is the same way. Water runs down the street then through 2 houses to the back of his lot and then runs to a ditch to Heatherdown. He added it’s all private property and the City cannot do it. Mr. Smith asked if there were easements, would they repair it. Dave told him NO. Mary added, you need to take care of your own yard. Amon said he deals with the constantly. He said the City could get easements and do it, but then they would have to do them all through town, and the money is not there for that. He added, this is not a unique situation; he said he could show in an hour’s time, 40 to 50 places that some places are better, some are worse. Mary again said people have to take care of their own property. Mr. Smith said she didn’t have any problem taking care of their own property; it was what was coming off of other people’s property that was the problem. Amon told Mr. Smith regardless of where you’re at, you are going to have water running across your property, and the further down you are, the more water you are going to have. That’s nature and there’s nothing the city or anybody else can do about that. Dave said the main problem he saw with this situation when he visited the property, was lot next door didn’t look like it was well kept. The ditch line hasn’t had any maintenance, so naturally there is going to be a buildup, and weeds, and it will make it difficult for the water to get through there. Mr. Smith said the property owners are not asking for the City to maintain it, but if it they ever got it to where it would drain, they (the owners) could maintain it. Dave told Mr. Smith the City would love to but they just can’t because it is private property. Amon suggested to Ms. Cedron to maybe get in contact with Mr. Willett, the owner of the lot, to see if he could maybe do something with the ditch. He said Mr. Willett called him in February to see if the City could help him with the ditch, but Amon told him he wouldn’t be able to. Amon said maybe the two of them could work something out. Dave mentioned it looked like at one time the ditch was on the property line, but it’s shifted onto the other property. Mr. Smith then asked if the Street Department didn’t have a problem with dumping water into the creek. Amon asked where else can it be dumped, or what would be the other option? Mr. Smith then asked if there were not requirements on how it is dumped. Amon told him the water will go to the least resistance. Mary added it will end up in the creek sooner or later, wherever it is. She told Ms. Cedron the committee appreciates her coming in with her concerns.  

The meeting was adjourned at 1:00 p.m.

Street Committee Meeting, July 14, 2009 – 12:30 p.m.

The meeting was called to order at 12:30.

Present were Amon Tilley, Director of Streets; Mary James, Darrel Bennett and Dave Almond, committee members.

The Street Report for June 2009 was passed out for review.

The Arkansas Avenue Phase 2 project is going well with a cost of $136,377.20 to date.

North Cardinal Drive has the curbs in and will be ready for paving this fall. Amon added that Arkansas Avenue Phases 1 and 2 along with Wallace Knob Road will be ready for paving sometime in August.

The ditch at North College Street at the elementary school is being concreted. When that is done, the crew will install a 4-foot high chain link fence around it since it is right by the playground. Mary said this is wonderful and it needed to be done.

The Keller Park Walking Path hasn’t had much done to it lately due to the weather, but the sub grade is done. Amon said this should be ready to pave before long. This project is being completed with a Grant. Amon reported the Budget is in good shape, and the department is still waiting for reimbursement from FEMA for the ice storm. The meeting was adjourned at 12:43 p.m.

  Copyright 2004.  A Spider Web Design Home News Project Pictures Street Committee FAQ